Site on the first day of earth moving, September 26, 2012.
Pistol bays are starting to take shape to the right.
Location of the clubhouse.
Rife Range, 200yd on left, 100yd on right.
Trap range view.
Footings are ready to go.
Pistol Bay 2 - 60' x 100'
Pistol Bay 1 - 40' x 100'
Footings have been poured, ready for the walls.
Pistol Bay 5, 100' x 100'
Walls ready to be poured.
Adding concrete to the wall forms.
We have walls!!
Note the openings for the air handler for the indoor range.
Bays are being built up.
Ready for Pre-Cast installation on Monday, once that is complete they should start framing the week of November 5.
Back filling underway.
Getting ready for pouring the basement floor.
Berms with 12′ sides & 15′ back berms,
Framing on the clubhouse underway.
Sewage grinder and retaining wall being added.